Four affordable-rent flats in Godalming, delivered with air-source heat pumps, photovoltaic roof tiles and enhanced insulation.
- Location
- Godalming, Surrey
- Sector
- Affordable housing
- Client
- Waverley District Council
- Project start
- March 2024
- Project end
- March 2025
THE PROJECT
The contract covered the removal of hardstandings and the design and construction of four apartments with associated external works.
CONSIDERED CHOICES
Air-source heat pumps provide heating, supported by a large array of photovoltaic roof tiles. Enhanced insulation improves on Building Regulations by around 10%.
Soakaways reduce surface-water discharge and around half of loose materials were purchased from local suppliers to reduce delivery emissions.
PROJECT DELIVERY
The team coordinated a four-metre-deep drainage connection, a temporary right-of-way diversion, utilities in the sole access road and remediation of hydrocarbon-contaminated soil.
Restricted access and limited storage were managed through smaller vehicles, off-site waiting areas and just-in-time deliveries. Residents received regular newsletters and programme updates.